How Sh2bn vanished in a stalled Treasury data recovery centre

Treasury entered into contract for the centre to create critical backup of financial data and other critical information in the event of a disaster.

image
by MOSES ODHIAMBO

Realtime01 March 2025 - 05:24
ADVERTISEMENT

In Summary


  • The project was awarded to Misort Africa Ltd in 2009 and was to be executed within 96 weeks at Sh782 million.
  • However, the scope was later increased and the project divided into three phases of implementation.